Senate Renews Push to Release NRMA EV Charging Report

Australia’s Senate has set a third deadline for the release of an NRMA report on delays to a national charging network, but its findings remain redacted.

Senate Renews Push to Release NRMA EV Charging Report
Photo: Djm-leighpark / CC BY-SA 4.0

The short answer: The Senate has passed another resolution seeking the NRMA’s “Grit in the Gears” report on delays to a national EV charging plan. The report remained redacted after the latest deadline, according to The Driven.

Australia’s Senate has passed a third resolution calling for the release of an NRMA report on problems with a publicly funded national EV charging rollout. The report, titled “Grit in the Gears,” could explain why the motoring group has completed only part of a planned 117-station network, leaving buyers and communities without a full account of delays to a major charging project.

The Coalition moved the latest resolution, which passed 35–20 with support from the Greens and independents, according to The Driven. It set November 25 as the new deadline. The Driven reported on November 26 that there was no evidence the report had been released by then.

The dispute concerns public accountability for a project intended to put charging stations along major routes across Australia. Slow delivery can affect the usefulness of long-distance EV travel, particularly in regional areas where alternatives may be limited. The Senate’s repeated requests show that lawmakers are still seeking a clearer explanation of what went wrong and what remains to be completed.

What the Senate is seeking

The Senate first called for the report’s release in September and later set an October deadline, The Driven reported. The November vote was the third resolution seeking publication. The report is described as a 21-page account subtitled “Lessons from the frontline of building a national EV network.”

The document has appeared on the Department of Climate Change, Energy and the Environment website, but its contents are redacted apart from one line identifying an average installation cost of $350,000, according to The Driven. That figure is the only part of the report the outlet said was visible. Its publication in redacted form therefore has not answered the Senate’s request for the underlying account of the project’s difficulties.

Energy and climate minister Chris Bowen previously refused the request, citing commercial sensitivity and claiming public immunity, according to The Driven. The outlet did not report that the minister had changed that position following the third resolution. Nor did it report that the redactions had been lifted by the latest deadline.

A network behind schedule

The NRMA won the contract in April 2023 to build 117 charging stations around Australia. The plan was backed by $78 million: $39 million from the Australian Renewable Energy Agency, or ARENA, with the NRMA agreeing to contribute an equal amount, The Driven reported. The target was to establish a charger every 150 kilometers along major routes.

Progress has fallen short of that target. An NRMA spokesperson told The Driven that about 62 stations had been completed. The outlet said the NRMA maintained that work was continuing on the remaining installations. That completion figure is higher than the 45 stations reported by the Australian Financial Review in March, which The Driven cited as a little more than one-third of the original target.

The two figures refer to different reported points in the rollout: the AFR’s March count was 45, while the later figure attributed to an NRMA spokesperson was about 62. The newer count indicates that installation continued, but it still leaves the network below its 117-station goal. The Driven did not report a revised completion date for the remaining sites.

The network’s intended spacing matters because it was designed to connect routes across a large country, including places beyond major population centers. A gap in a route can limit the practical value of stations that are already open: drivers may need the network to work as a connected chain, rather than as isolated charging locations. The source does not quantify how many routes remain incomplete or how often drivers have been affected.

Known obstacles in the rollout

Although the “Grit in the Gears” report is redacted, a separate ARENA report published in late December 2024 described several problems encountered during the program, according to The Driven. These included charging hardware flaws, supply-chain constraints, local council rules, site approvals and delays in connecting locations to electricity networks.

The ARENA report said hardware design defects were sometimes discovered only after equipment had been deployed. Some station designs needed complete redesigns, delaying installation and requiring the NRMA to renegotiate arrangements with site hosts. The report said this exposed a broader challenge: emerging charging technologies may receive extensive testing only after field deployment, allowing faults to surface when projects are already underway.

Those problems can affect more than the equipment itself. A redesign may require changes to a site’s infrastructure and renewed agreement with the host, extending the time before a charger can open. The ARENA account, as quoted by The Driven, connected the hardware issues to delays in the installation schedule. It did not establish that every incomplete station was delayed for the same reason.

Supplier changes added pressure. The Driven reported that the withdrawal of charging companies Tritium and Freewire from the Australian market complicated the rollout. The outlet did not specify how many stations depended on either company or attribute a particular delay to either withdrawal.

Site conditions and approvals also created obstacles. The ARENA report cited negotiations over Crown land, floodplain impacts and underground utilities that had not been recorded. These issues emerged during detailed site assessments, according to the report. They can require changes to plans or additional work before construction and electrical connections proceed.

Grid access was another bottleneck. The ARENA report described delays securing connections from distribution network service providers, or DNSPs, and uncertainty around tariffs. It also said approvals for newer arrangements such as behind-the-meter batteries were slow, affecting some locations and requiring changes to project timelines and budgets. The report characterized grid connections as among the most time-consuming parts of the work.

Finally, the ARENA report raised concerns about lower-than-expected use at some remote locations. It said that experience pointed to the need for more strategic site selection, because some locations proved less viable than anticipated given limited demand. That finding concerns utilization at certain sites; it does not, by itself, explain the overall shortfall in completed stations.

Why publication matters

The separate ARENA report offers examples of practical barriers, but it is not a substitute for the redacted “Grit in the Gears” account that senators have requested. The Senate is seeking the NRMA report itself, and the public version currently described by The Driven reveals almost none of its contents beyond the average installation cost.

For EV buyers, the unresolved issue is whether the national network will be completed and when. The available reporting confirms that the NRMA says installation is continuing, but gives no new finish date. For governments and charging operators, the accounts of hardware redesigns, supplier departures, site constraints, approvals and grid connections show why delivery depends on more than choosing locations and installing chargers. The sources do not establish which of those challenges accounts for the largest share of the shortfall.

The latest resolution renews pressure on the government to release the report, but the vote alone does not reveal whether the redactions will be removed. As of The Driven’s report on November 26, the latest deadline had passed without evidence of publication in an unredacted form. The outstanding questions are what the NRMA’s own review concluded, whether it identifies additional causes, and how the remaining stations will be delivered.

Frequently asked questions

What is the “Grit in the Gears” report?

It is a 21-page NRMA report subtitled “Lessons from the frontline of building a national EV network.” The Senate is seeking its release to understand problems with the charging rollout.

How many charging stations are complete?

An NRMA spokesperson told The Driven that about 62 of the planned 117 stations had been completed. The NRMA said work was continuing on the others.

Why has the report not been released in full?

Energy and climate minister Chris Bowen previously refused the request, citing commercial sensitivity and claiming public immunity, according to The Driven. The public version is redacted apart from a line stating an average installation cost of $350,000.

What problems affected the charging rollout?

A separate ARENA report cited hardware design flaws, supply-chain constraints, council and site approvals, difficult site conditions, grid connection delays, tariff uncertainty and low utilization at some remote sites.

Sources: thedriven.io