Canadian EV Charger Projects Stall Over Permits and Utilities
A Canadian charging industry survey links stalled fast-charger projects to parking rules, lengthy municipal approvals and utility connection delays.
The short answer: Municipal permitting rules and utility connection delays are slowing Canada's public fast-charger rollout, according to Electric Autonomy. Seven survey respondents reported abandoning 54 sites over two years, with municipal or utility obstacles accounting for half.
Municipal parking rules and utility connection problems are delaying public fast-charger construction in Canada and contributing to canceled projects, according to Electric Autonomy. A charging industry survey found that seven respondents abandoned a combined 54 sites over two years after reaching agreements with property hosts. Half of those sites were dropped primarily because of municipal or utility obstacles, preventing projects from becoming charging locations for EV drivers.
The findings put the approval process for chargers in existing parking lots under scrutiny. Operators say requirements intended for new developments can complicate these retrofits, raising costs and sometimes stopping projects outright. The Canadian Charging Infrastructure Council, or CCIC, is calling for clearer municipal requirements, simpler approval pathways and decisions on complete applications within three months, Electric Autonomy reported.
Parking requirements are a leading obstacle
The CCIC survey, titled Hearing from the experts: Survey findings on municipal approvals, utility connections, and public fast-charging deployment in Canada, drew responses from nine organizations. Seven were charging network operators and two were engineering and construction contractors, with experience spanning eight provinces, according to Electric Autonomy.
Land-use requirements were the most common sources of delay for fast-charging installations in existing parking lots. These included minimum parking requirements, landscaping rules and site plan reviews. Seven of the nine respondents said parking minimums had delayed at least one project during the previous two years, making them the most frequently reported obstacle.
The parking issue stems from how municipalities count spaces. Chargers usually occupy parking stalls, which can leave a property below its required number of spaces, Electric Autonomy reported. That creates an approval problem even when a property owner has agreed to host charging equipment. The council wants municipalities to count charging stalls toward their parking requirements, addressing that specific barrier.
Operators also face different interpretations of approval requirements within the same province. Of the eight respondents who answered that question, seven reported moderate to extreme variation in how municipalities handle the same type of approval. For charging developers working across multiple communities, that finding points to a process whose requirements depend heavily on the location.
Approval timelines miss operators' expectations
Eight of the nine survey respondents said a permit for a parking-lot retrofit should take less than three months. Among respondents who reported their typical approval timeline, none said approvals arrived that quickly. Typical waits ranged from three to 18 months, according to Electric Autonomy.
Those figures describe municipal approval timelines reported by the participating organizations. Utility connections were a separate source of difficulty in the survey, showing that a project can face obstacles both in obtaining permission for a site and in arranging its electrical service.
The abandoned-site figures show the consequences beyond longer schedules. Seven respondents reported dropping 54 sites after securing agreements with hosts. Ten were abandoned primarily because of municipal delays or denials, while 17 were abandoned primarily because of utility connection delays or costs. Together, those 27 sites accounted for half of the total.
The survey draws on the experience of a small group of industry participants rather than a count of every charging project in Canada. Its geographic reach nevertheless extends across eight provinces, and the responses identify recurring problems with parking rules, municipal consistency and electricity connections. For drivers, the practical consequence is that an agreement to install chargers at a property does not necessarily result in an operating station.
Ontario report describes longer delays
A separate report from The Atmospheric Fund, or TAF, adds an Ontario example to the council's findings. Released in September, its Red Tape Reduction Opportunities for the Province of Ontario report said some charging project approvals in the province had taken more than 30 months, according to Electric Autonomy.
TAF highlighted five planned On the Run EV Fast Charge projects in Hamilton. Those projects stalled amid repeated municipal and utility delays and are now unlikely to proceed. The example illustrates how both approval systems can affect the same group of proposed stations, rather than presenting developers with only one isolated obstacle.
TAF wants Ontario to give municipalities a toolkit for streamlined permitting, including guidance defining how charging should be classified under zoning bylaws. It also proposed that the province adopt an EV readiness policy similar to recent changes to Quebec's construction code. Those recommendations would put provincial guidance behind local decisions about charging development.
The organization also called for eliminating minimum parking requirements across Ontario. That proposal goes further than the CCIC recommendation to count charging stalls toward required parking totals, although both address the role parking rules play in charging projects.
Proposals address access and charging costs
TAF's recommendations extend beyond permitting. It called for opening surplus public land and parking facilities to charging operators, waiving parking fees for drivers using those chargers and reducing rents for operators. TAF estimated that those measures could cut charging costs for urban drivers by 33% to 65%, Electric Autonomy reported.
That range is an estimate associated with the proposed measures, rather than an announced reduction in charging prices. It connects access to public property and the costs of using that property with the affordability of charging for urban drivers.
The CCIC's municipal recommendations focus on making straightforward installations easier to approve. Along with counting charging stalls toward parking requirements, the council wants a “minor works” or as-of-right pathway that would spare simple retrofits from a full permit review. It also wants published requirements and a single point of contact, giving developers a clearer route through the process.
The council's proposed three-month deadline applies to decisions on complete applications. Together, its recommendations target the issues respondents described: lengthy reviews, inconsistent treatment between municipalities and requirements that complicate installations in existing parking lots.
Toronto and Surrey offer examples of changes
Some utilities and municipalities have already taken steps to simplify charging projects. Toronto Hydro launched a pilot in April that delivers 480-volt service directly to public fast-charging sites, according to Electric Autonomy. Most fast chargers operate at 480 volts, while the utility's transformers have typically delivered 600 volts.
That voltage difference has required developers to buy and maintain their own step-down equipment. Under the pilot, Toronto Hydro owns and maintains the 480-volt transformer, while customers pay for its installation. The program changes who owns and maintains that equipment, addressing a specific part of the electrical connection process.
The Toronto Hydro pilot is capped at 10 projects and runs through the end of 2027. Its limited scope means it represents a defined trial of a different service arrangement, with the utility taking responsibility for transformer ownership and maintenance at participating sites.
In British Columbia, Surrey worked with charging providers to clarify which station designs and locations could qualify for faster approvals. The municipality also publishes an EV charger installation framework setting out engineering requirements. According to Electric Autonomy, that guidance is intended to improve clarity and avoid repeated revisions.
The next steps sought by the CCIC are broader adoption of clear requirements, simpler review pathways and shorter decision timelines. Toronto Hydro and Surrey offer examples of changes already underway, while the council's survey documents the municipal and utility obstacles that continue to delay or end proposed charging projects.
Frequently asked questions
Why are public fast-charger projects being delayed in Canada?
According to Electric Autonomy, a Canadian Charging Infrastructure Council survey identified parking minimums, landscaping rules, site plan reviews and utility connection delays or costs as obstacles. Respondents also reported inconsistent approval processes between municipalities.
How many charging sites were abandoned?
Seven survey respondents reported abandoning 54 sites over two years after securing host agreements. Ten were dropped primarily because of municipal delays or denials, and 17 primarily because of utility connection delays or costs.
How long do municipal approvals take?
Respondents who reported typical approval timelines described waits of three to 18 months, according to Electric Autonomy. A separate Atmospheric Fund report said some charging project approvals in Ontario had taken more than 30 months.
What changes does the charging council recommend?
The CCIC wants municipalities to count charging stalls toward parking requirements, simplify reviews for straightforward retrofits, publish clear requirements, establish a single point of contact and decide complete applications within three months.
What is Toronto Hydro doing to simplify fast-charger connections?
Toronto Hydro is running a pilot that delivers 480-volt service directly to public fast-charging sites. The utility owns and maintains the transformer, while customers pay for installation. The pilot covers up to 10 projects and runs through the end of 2027.
Related stories
How to Build a Flexible EV Charging Routine for Work
Build charging around the miles you need for your next drive, using home, work, or public charging as your schedule allows. Keep a practical buffer.
How to Check EV Charger Plug Compatibility Before a Trip
Match your EV’s connector and charging limits to each route stop. Learn what charger labels mean, when an adapter may work, and what to confirm before you leave.
How to Estimate Electric Car Range While Towing
Estimate towing range from your vehicle’s normal range, then adjust for trailer shape, speed, weather and hills. Use the result to plan charging stops.